Barnesville’s 2025 Street Improvement Program Begins
The village’s 2025 Street Improvement Program starts tomorrow and will go through Sept. 22. Cast & Baker Corporation will complete the project.
The following tentative schedule is subject to change in regards to weather delays, equipment breakdowns and production.
9/10 Pine Lane – Pavement Planing
9/10 Clifton Street – Pavement Planing
9/10 Cherry Street – Pavement Planing
9/11-9/12 Pine Lane – Pavement Repair/Asphalt Paving
9/12 Clifton Street – Asphalt Paving
9/15 Clifton Street – Asphalt Paving
9/15-9/16 East Church Street
9/17 Walton Street – Pavement Planing
9/17 Cole Street – Pavement Planing
9/17 Washington Street – Pavement Planing
9/17 West Main Street – Pavement Planing
9/18 Cherry Street – Asphalt Paving
9/18 Walton Avenue – Asphalt Paving
9/19 Cole Street – Asphalt Paving
9/19 Washington Street – Asphalt Paving
9/22 West Main Street – Asphalt Paving
Village officials are asking residents not to park on these streets during paving so crews can complete the work.
Residents enrolled in the CodeRED alert system will receive updates by phone and text. Others can sign up through the village website.
Barnesville Area News Needs Your Support!
We're dedicated to providing coverage of the local happenings in Barnesville and the neighboring communities.
As a non-profit entity, we rely on the donations of readers like you.
Make a donation today and you'll be helping keep local news alive in the Barnesville area.